Cabinet will be asked to:

1. Agree the Phase II Masterplan and Business Plan for the Bretons site,

including the Manor House, Barns, outbuildings, walled garden, lake and park

as set out in the report and appendices.

 

2. Agree that an outline planning application for the Phase II Masterplan is

submitted.

 

3. Agree to progress elements of Stage 1 of the Masterplan Business Plan -

Creation of two new 3G pitches, Sports Pavilion, car park extension and urgent remedial works to the Manor House to include detailed design, planning and funding applications.

 

4. Delegate authority to the Chief Operating Officer, after consultation with the

Leader and Cabinet Member for Public Protection and Safety, to authorise the

submission of related funding applications to external bodies to a limit of £10m and enter in to such grant agreements as may be required.

Decision type: Key

Reason Key: Expenditure > £500,000;

Decision status: Redraft Awaited

Notice of proposed decision first published: 26/08/2021

Exempt information notice

It is anticipated that this report will contain information which is exempt from publication and during discussion of this information the public may be excluded from the meeting. View the reasons for the exemption

Representations on exempt information

If you wish to make representations that the public should not be excluded from the meeting during discussion of this item please write to Democracy Services Manager stating the reasons why you think the discussion should be held in public

Decision due: 10 Nov 2021 by Cabinet

Lead director: Chief Operating Officer

Contact: Guy Selfe, Health and Wellbeing Manager Email: guy.selfe@havering.gov.uk.

Consultation process

User groups at Bretons have been consulted and in addition, the Essex Football Association will also be consulted.