Issue details
Capital Budget Proposal for Street Lighting upgrades using Salix and Business Risk Reserve Funding
The Director will be asked to approve:
- That £0.450m of the existing Salix Recycling fund is committed to upgrade the existing street lanterns to LED.
- That £0.346m of existing Business Risk Reserve funding is committed to also upgrade street lanterns to LED.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 03/06/2019
Decision due: Not before 9th Jul 2019 by Statutory Section 151 Officer Finance
Lead member: Cabinet Member for Environment
Lead director: Director Neighbourhoods
Department: Neighbourhoods
Consultees
All relevant Members, officers and business partners will be consulted.
Decisions
- 18/07/2019 - Capital Budget Proposal for Street Lighting upgrades using Salix and Business Risk Reserve Funding
Documents