Agenda item
Sheltered Housing Lift Project
Decision:
Report: Sheltered Housing Lift Project
Presented by: Councillor Paul McGeary, Cabinet Member for Housing & Property
Cabinet
Approved the award of a contract to build the nine lifts to Kirkman and Jourdain Ltd, at the cost of £1,438,813 with the contract estimated to commence late July 2024 and conclude October 2025.
Minutes:
Report: Sheltered Housing Lift Project
Presented by: Councillor Paul McGeary, Cabinet Member for Housing & Property
Summary
This report concerns the award of a contract, after a compliant tender process, for the construction of nine lifts housed in small extensions at three two-storey sheltered schemes in Havering.
The works were requested due to sheltered scheme residents having increasing issues with mobility therefore finding stairs difficult. It was agreed to investigate the possibilities and, subsequently after some consultation, look at design options. Planning consent was obtained for the works.
The works were tendered following approval of the non-key ED giving authorisation to seek tenders. A compliant tender process was undertaken in accordance with that authorisation and bids were evaluated on a 70/30 price/quality ratio. The tender process was reviewed and approved by the Procurement Gateway Review Group on 9th May 2024. More detail can be found in exempt appendix A.
The most economically advantageous tender, submitted by Kirkman and Jourdain Ltd, is within budget at £1,438,813.
Cabinet
Approved the award of a contract to build the nine lifts to Kirkman and Jourdain Ltd, at the cost of £1,438,813 with the contract estimated to commence late July 2024 and conclude October 2025.
Supporting documents:
- 9.0 Cabinet report on Sheltered Housing Lift Project-V4, item 211. PDF 306 KB
- Restricted enclosure View the reasons why document 211./2 is restricted
- 9.2 Appendix B-EqHIA-Sheltered Housing Lift Project-V1, item 211. PDF 1 MB