Agenda item

Large Complex Works and Street Retrofit

Decision:

Cabinet:

 

 

1.     Approved the procurement of two contracts of a total value of up to £350m for a term of 10 years with the option to extend for 6 years, for the provision of major works, primarily for Council housing but with Corporate buildings within scope.

 

2.     Approved a waiver of the Council’s default evaluation criteria of 70% Price: 30% Quality and instead award the contracts on the MEAT basis of a 50% Quality, 40% Price, and 10% Social Value weighting for the reasons set out in Section 2 of this report, Procurement Proposals.

 

3.     Approved the use of the Mercell portal managed by Lumensol Limited, the Council’s appointed consultant, for reason set out in Section 2 of this report, Procurement Proposals.

 

4.     Delegated approval of the award of the contract and to enter into contract terms post tender with the winning bidder to the Strategic Director of Place, acting in consultation with the Lead Member for Housing, the Strategic Director of Resources and the Deputy Director of Legal & Governance.

 

5.     Delegated the award of works packages under the contract to the Strategic Director of Place, acting in consultation with the Lead Member for Housing.

 

Minutes:

Report Title: Approval to Tender and Award of Two Contracts for Large Complex Blocks and Street Retrofit

 

Presented by: Councillor Paul McGeary – Cabinet Member for Housing and Property

 

Summary:

 

These contracts provide a framework that will enable the Council to comply with its statutory requirements.

 

This work supports the Housing Asset Management Strategy 2021-26 and is identified within the HRA Business Plan approved by Cabinet in February 2024

 

1. As part of the Council’s responsibility as a landlord, the Council has a duty to undertake repairs, maintenance, refurbishment, improvements and compliance checks on its Housing Revenue Account (HRA) housing stock. This report presents to Cabinet details of the proposed tender process to procure contracts to deliver a number of these services and seeks approval to procure and delegated approval for the subsequent award of two separate contracts.

2. The current HRA annual budget for major works within the scope of these contracts is approximately £21million per annum. The primary purpose of these contracts is to allow the necessary major works to be carried out in an holistic manner, giving consideration to the programming of different refurbishment works and the co-dependence of different drivers such as Decent Homes, damp and mould, building safety and zero carbon.

3. Monies have been identified within the HRA 30-year business plan and contract spend will be aligned with business priorities and approved budgets on an annual basis

 

 

Cabinet:

 

1.     Approved the procurement of two contracts of a total value of up to £350m for a term of 10 years with the option to extend for 6 years, for the provision of major works, primarily for Council housing but with Corporate buildings within scope.

 

2.     Approved a waiver of the Council’s default evaluation criteria of 70% Price: 30% Quality and instead award the contracts on the MEAT basis of a 50% Quality, 40% Price, and 10% Social Value weighting for the reasons set out in Section 2 of this report, Procurement Proposals.

 

3.     Approved the use of the Mercell portal managed by Lumensol Limited, the Council’s appointed consultant, for reason set out in Section 2 of this report, Procurement Proposals.

 

4.     Delegated approval of the award of the contract and to enter into contract terms post tender with the winning bidder to the Strategic Director of Place, acting in consultation with the Lead Member for Housing, the Strategic Director of Resources and the Deputy Director of Legal & Governance.

 

5.     Delegated the award of works packages under the contract to the Strategic Director of Place, acting in consultation with the Lead Member for Housing.

Supporting documents: