Issue - meetings
BEAM PARK STATION - GAS PIPELINE
Meeting: 16/05/2017 - Rainham & Wennington and South Hornchurch Working Party (Item 31)
31 BEAM PARK STATION - GAS PIPELINE PDF 150 KB
Additional documents:
Minutes:
The Working Party received a presentation that outlined Beam Park Station and the gas pipeline along its proposed route.
The Working Party was informed that following an extensive investigation the conclusion was that the gas pipelines should not be an obstacle to the station project, but may require some protection during the construction process.
It was mentioned that the gas pipelines along the site and route would pose no risk to the development of the station building.
The Working Party noted that the Health & Safety Executive would be involved in any construction that would be undertaken at the site.
The Working Party noted the presentation.